Public conflict over spending control
Nikolai Kalashnyk, who holds the post of Minister of Restoration, provided comments on the state of construction of protective engineering structures at energy facilities in Kyiv Oblast after a long pause in the media space. He stated directly that during his leadership of the Kyiv Oblast Military Administration (OVA), the functions of controlling the fulfilment of contractual obligations were assigned to then-deputy Ruslan Oliinyk, who recently left his position as deputy minister.
Project details and financial indicators
On 14 November, Kalashnyk held a meeting with journalists. He noted that construction works began in autumn 2025. Priority substations were identified by the company DTEK Kyiv Regional Power Grids. According to the resilience plan, it was envisaged to create a second level of engineering protection for transformers at 26 substations with a voltage of 110 kV.
The customer was the Department of Regional Development of the Kyiv OVA, which was responsible for concluding agreements and transferring funds. As Kalashnyk explained, control over the implementation of the relevant OVA order was assigned to his then-deputy Ruslan Oliinyk.
The project had the status of a government experiment, which allowed concluding direct contracts without conducting tender procedures. The General Staff approved the first standard solution, and the project documentation underwent expert review at the Kyiv Scientific Research Institute of Forensic Expertise.
During Kalashnyk's leadership of the OVA, contractors received UAH 621.3 million in advances from the state budget. After 17 July, an additional UAH 290.1 million was transferred from the state and regional budgets. The total amount of prepayment to contractors amounted to UAH 911.4 million.
Dynamics of construction readiness
As of 16 July, when Kalashnyk left the post of head of the Kyiv OVA, the overall construction readiness of the facilities was 40.02%. By 5 October, this indicator had increased only to 46.75% (approximately 0.6% per week). At such rates, the region risked failing to meet the established deadlines. On 5 October, the risk of missing the deadline was noted at a meeting of the Coordination Centre chaired by the Prime Minister. Following this, the Ministry of Infrastructure took over separate coordination of the works, and the rates increased to 1.6% per week. Currently, readiness stands at 55%.
Disagreements over the distribution of responsibility
Kalashnyk emphasised that he bears responsibility for decisions made during his leadership of the region. The facilities have been proposed for transfer to the Restoration Agency, and the State Audit Service is being involved to conduct an audit. The issue of the legality of the actions of officials and contractors falls within the competence of law enforcement agencies.
Oliinyk claims that the Department of Regional Development was not subordinate to him, and the curator was the relevant deputy, close to Kalashnyk. According to him, the implementation of resilience plans was one of the key tasks of the head of the OVA, Kalashnyk personally reported weekly on the progress of the works, and it was impossible to conclude contracts for 26 facilities without his approval and direct instruction. At the same time, everyone understands that it is Kalashnyk who bears direct political responsibility for this situation.